Increasing Production Enhancement by Using Progressing Cavity Pump

Project : MINI EPF  PLAN C

Field : ERAWIN

Client : ZALLAF OIL COMPANY    

CLIENT PROBLEM STATEMENT

  • The client intends to increase oil production to 10,000BPD.
  • Connected tie-In 6Inch Pipeline that connected Plan B to Plan C without any commissioning.

ALFANOIL Solution

  • The increase in production flow rate from 6,000 bbl/day to 10,000 bbl/day by installed pipeline and pump station to meet client production to meet 10,000 BPD.
  • Tie-In with 6 Inch pipeline that connected Plan B with Plan C.
  • This step allowed Zallaf  to preformed commissioning to their pipeline.
  • Reduce the cost of client by Change of transport Oil by pipeline instead of Trucks.